By the President; The first steam unit of Ferdowsi power plant was inaugurated
Simultaneously with the 30th week of #every_week_of_of_Iran_A_B, the first steam unit of Ferdowsi Combined Cycle Power Plant with a credit of 3,400 billion Tomans was inaugurated this morning by video conference by the President.

In order to increase electricity production, respond to the growth of consumption in the region and also increase the efficiency of gas power plants by converting it into a combined cycle, the construction of three 160 MW steam units of Ferdowsi power plant in the form of Buyback projects is on the agenda.

The main mission of Buyback projects is to build a combined cycle steam power plant from fuel-saving resources; In this regard, the construction of the steam section of Ferdowsi power plant has been concluded during a reciprocal sale contract with Toos Mapna Power Generation Company, and the mechanism of return on investment will be from fuel savings.

In gas power plants, the exhaust heat of the units is released to the outside environment from the exhaust of the gas sector with a temperature between 540 and 600 ° C, which in addition to wasting energy, increases the emission of greenhouse gases.

In this project, by using the exhaust heat of the gas units and directing it to the equipment of the steam sector, electrical energy is generated, which produces 250 million cubic meters of fuel per year per unit of steam.

Accordingly, with the completion of the steam units of this power plant, 756 million cubic meters of fuel consumption will be saved annually.

On the other hand, Ferdowsi power plant currently has 6 gas units with a total capacity of 954 MW, which with the completion of three steam units of the power plant, the capacity of this complex will reach 1,431 MW and its efficiency will reach about 50%.

Tarztalab, the CEO of Thermal Power Plants Holding Co. announced last day: “The main mission of cross-selling projects is to build a steam section of a combined cycle power plant from fuel-saving resources; Accordingly, the construction of the steam section of Ferdowsi power plant has been concluded during a buyback contract with Toos Mapna Power Generation Company, and the mechanism of return on investment will be from fuel savings.

Tarztalab emphasized that by completing the steam units of this power plant, 756 million cubic meters of fuel consumption will be saved annually, adding: "Currently, this power plant has 6 gas units with a total capacity of 954 MW, which with the completion of three steam units of the power plant 1,431 MW and its efficiency will reach about 50%.”