According to TPPH’s public relations
and international affairs, by exploiting the second unit of Samangan combined cycle power station, by
exploiting the second gas unit of Samangan power station the electricity
generation capacity of Samangan power sation’s capacity reached up to 332
megawatts and Shobad (Kahnouj) combined cycle power station’s capacity reached
up to 484 megawatts.
Kahnouj combined cycle power station is
constructed by private investment in two gas and one steam unit and
is situated in 15th kilometre of Kahnouj-Jiroft Road and Samangan
combined cycle power sation is situatited in 10th kilometre of
Sirjan-Kerman Road in Kerman province.
By exploiting
of these power plant units, the
private sector’s share in electricity generation in the whole country reached
up to 11785 megawatts from power station units in the new Persian fiscal year
reached 1314 megawatts in 77 power plant units and the amount of thermal power
generation by Thermal Power Plant Holding will reach up to 37834 megawatts on
253 power plant units.
By exploiting
the second gas unit of Samangan combined cycle
power station with 166 megawatts, the total capacity of the power station’s gas
unit will reach up to 322 megawatts which will be synchronized to Iran’s
national electricity network.
It is estimated that the steal unit of
Samangan combined cycle power station wth 160 megawatts capacity will be
exploited in next summer.
Samangan combined cycle power station is under construction by the
investment of Qods niru, Kerman Tableau and Kani Mess Companies and Shobad
(Kahnouj) combined cycle power station is under construction by the investment
of Arianmah Tabgostar company both in Kerman province. MAPNA Company is the contractor for both combined cycle power
stations.