TPPH’s CEO Mohsen Tarztalab Announced the Exploitation of Kahnouj Power Plant and the Start of 5000 Megawatts in a New Power Plant Construction Project
11/14/2016
Chief Executive Officer of Thermal Power Plant Holding’s(TPPH) Parent Company, Moshen Tarztalab says: “Exploitation of Kahnouj Power Plant with 484 Megawatt capacity and execution project of 5000 Megawatts of capacity combined cycle power plant will be started by Tuesday November the 15th.

According to Theraml Power Plants Holding’s (TPPH) public relations and international affair’s office, Mohsen Tarztalab announced in a press conference that: “Shobad Kahnouj combined cycle power plant with the capacity of 484 Megawatts will be exploited.

According to the statement of this official figure, the start of the construction of 28 new power plant units in eastern, northern and southern region of the country will be done this Tuesday November the 15th.

“The projects which are ready to start includes Bandar Abbas, Tous, Urmia, Haris, Maku, Kashan, Jahrom, Qeshm 2, Assalouyeh, Western Mazandaran and Roudshour power stations that six projects among them are in buyback form, 1 will be done by private sector and four projects will be done by Thermal Power Plants Holding.

Tarztalab explained Kahnouj’s Shobad power station’s characteristics as a combined cycle power station with two gas units with 162 Megawatts capacity and a steam unit with 160 Megawatts capacity. The power station is constructed by the investment of a domestic company with the value of 310,000,000. Bank Sanat va Madan is responsible to transfer finances.

Chief Executive officer of Thermal Power Plants Holding (TPPH) added: “The capacity of power station’s post is 230 kilovolts and two fuel storage each with 15,000,000 meter squares capacity in the sight of power station is constructed. For main fuel of the units, gas and as the second fuel, gasoline is predicted.”

“Along side with this project, the executive action of 5,000 Megawatts in new power station is done in form of 12 projects in 10 provinces from this Tuesday. 2,800 Megawatts are newly made power plants and 2,200 Megawatts is to accomplish gas units of power stations.” He added.

“In conclusion, TPPH in terms of resistant economic policies, has planned 17,000 Megawatts power plant capacity in current 2016-2017 Persian fiscal year that we can say Tuesday November the 15th is the start date of 5,000 Megawatts of them.” He concluded.